Short answer
A notice to complete is a formal letter one side serves when the other has missed the completion date. Under the Standard Conditions of Sale it gives 10 working days to complete, and time becomes of the essence. If a buyer still does not complete, the seller can end the contract, keep the deposit, resell and claim damages.
On this page
- Notice to complete at a glance
- What is a notice to complete?
- Who can serve a notice to complete, and when?
- How long does a notice to complete last?
- What must a buyer do when a notice to complete arrives?
- What happens if you do not complete within the notice?
- Is a notice to complete different on a new-build home?
- Is there a template notice to complete letter?
- How do we deal with a missed completion date?
- Our fees
- What happens next
Notice to complete at a glance
| What it is | A formal notice served after a missed completion date, requiring completion within a fixed time |
|---|---|
| Who can serve it | A party who is ready, able and willing to complete, once the completion time on the completion date has passed |
| Time allowed | 10 working days, not counting the day of service; time is of the essence |
| Deposit top-up | A buyer who paid under 10% must pay the balance up to 10% at once |
| If the buyer does not complete | The seller may rescind, keep the deposit with interest, resell and claim damages |
| New builds | The notice is usually expected to give at least 14 calendar days |
What is a notice to complete?
Contracts fix a completion date. Usually the money arrives and the keys are handed over that day. When one side is not ready, the other side can lose weeks, a removal date and a connected purchase.
A notice to complete is the tool the contract gives the side that is ready. It turns an open-ended delay into a deadline. Before the notice, being late usually costs the late party compensation. After it, being late can end the contract.
It is a legal document, served by one side’s solicitor on the other side’s solicitor. It is not the same as a reminder email, and it is not the same as asking for an extension.
Who can serve a notice to complete, and when?
Either party can serve one, buyer or seller. The Standard Conditions of Sale, the Law Society’s standard terms used in residential sales, set the conditions.
| Question | Answer under the Standard Conditions of Sale |
|---|---|
| Who may serve it? | A party who is ready, able and willing to complete |
| When? | After the completion time on the completion date has passed. Not before |
| On whom? | The other party to the contract |
| How long does it give? | 10 working days, not counting the day it is served |
| What does “time of the essence” mean? | The deadline is strict. Missing it is a serious breach, not just a delay |
“Ready, able and willing” matters. A buyer who has no mortgage funds cannot serve one, and a seller who has not got the property ready to hand over cannot serve one either. A notice served by someone who is not ready may not be valid.
How long does a notice to complete last?
Under the Standard Conditions of Sale, 10 working days. The day of service is not counted, and the conditions define “working day” (it leaves out weekends and bank holidays), so your solicitor counts the days from the contract. Served on a Monday, with no bank holiday in between, the 10 working days end on the Monday two weeks later.
That is a rule of the standard conditions. A contract can say something different, so your solicitor reads the contract to check. For new-build homes, the developer’s contract has its own terms, and the New Homes Quality Code says the notice is usually expected to give at least 14 calendar days unless you and the developer agree otherwise.
The deadline is for the money to arrive. If your lender’s funds, or the funds in the chain above you, will not be there in time, tell your solicitor on the day the notice arrives.
What must a buyer do when a notice to complete arrives?
Act on the day it arrives. There are four things to settle at once.
Tell your solicitor and read the dates. Check the date of service and count the working days with them.
Top up the deposit if you paid less than 10%. The standard conditions say a buyer who paid a smaller deposit must at once pay the balance up to 10% of the price.
Confirm your funds. Ask your lender, and your solicitor if you are also selling, to confirm when the money will arrive.
Tell people in the chain. A buyer who cannot complete may hold up the sale of the home they are in. Your solicitor can warn the other solicitors.
What happens if you do not complete within the notice?
If the buyer fails to comply, the standard conditions let the seller do all four of these:
- End the contract. The seller can rescind, so the buyer no longer has a right to the property.
- Keep the deposit. The deposit is forfeited, together with the interest it has earned.
- Sell elsewhere. The seller is free to resell the property.
- Claim damages. If the resale price is lower, or the seller lost money, they can claim for that loss.
If the seller is the late party, what the buyer can do depends on the contract. If you are the buyer and the seller is the late party, your solicitor will explain what is open to you before you serve anything.
Because the stakes are high, many sales are rescued before the notice runs out. Parties agree a short extension in writing, or the funds arrive. Never rely on a spoken promise of more time.
Is a notice to complete different on a new-build home?
It works in a similar way, but the developer chooses the completion date. A developer usually serves the notice when the home is ready, and the buyer must then complete within the period it gives.
The New Homes Quality Code expects the notice to give at least 14 calendar days. For homes reserved on or after 2 March 2026 (Code version 2), a pre-completion inspection takes place after the notice is served and before completion, or earlier by agreement. Our guide to new-build warranties and snagging explains how to use that inspection.
Is there a template notice to complete letter?
Yes. We have a free template letter in Word and PDF that your solicitor can adapt. It is a starting point for a solicitor to review, not a form to send yourself.
- Word version. Notice to complete template (.docx), for editing.
- PDF version. Notice to complete template (.pdf), for reading.
A valid notice normally identifies the property and the contract, states the agreed completion date, says it is served under the contract’s notice to complete condition, names the time for completion and is dated. The contract also sets out how a notice must be sent. Get that wrong and the notice can fail, so leave service to your solicitor.
How do we deal with a missed completion date?
The first step is to find out why completion has not happened. We speak to the other solicitor and to your lender, and tell you where the money is. Often the call is enough.
If the other side is not going to complete, we advise you in writing on whether serving a notice is right, check you are ready, able and willing, and serve it in the way the contract requires. If a notice has been served on you, tell us at once and we go through the deadline with you, and you get a written, itemised quote before you instruct us.
Our fees
| Buying a residential propertyStandard purchase of a freehold home under £2m, with one mortgage | £1,210 – £2,010 + VAT (£1,452 – £2,412 including VAT) |
|---|---|
| Selling a residential propertyStandard sale of a freehold home under £2m, with one registered mortgage to redeem | £790 – £1,135 + VAT (£948 – £1,362 including VAT) |
Typical ranges for a standard transaction, excluding VAT at 20% and disbursements. Every client receives a written, itemised quotation with an exact figure before instructing us. See all our fees and what they cover.
Free conveyancing quote
Get your fixed-fee quote in a minute
- Written, itemised quote
- No obligation
- Your details stay private
What happens next
Legally reviewed by Shah Ali, Senior Partner, on 18 November 2026.
Last updated 18 November 2026.
Sources
- The Law Society, Standard Conditions of Sale (Fifth Edition, 2018 Revision), checked 29 October 2026
- New Homes Quality Code, version 2, s2.7-2.8 (and version 1, s2.8), checked 29 October 2026
How this page was made: drafted with AI help from the Law Society’s Standard Conditions of Sale (Fifth Edition) and the New Homes Quality Code, then edited. Checked and signed off by Shah Ali on 18 November 2026.